Actual operation:
27% of commercial
vehicles (trailers) are checked in detail generating lines of over 3 kilometers
and wait times of over 3 hours.
Project and
Construction:
The checkpoint
“PRECOS Benjamin Hill, Sonora, México” will be relocated to KM. 112 of the Federal road MEX 015
Hermosillo Nogales. The project is currently in the revision process and the
implementation stages are being defined. The resources to start the construction
of access lines and platforms have been programmed for
2008.
New
facilities:
Permits:
SEMARNAT: Has
turned in the Resolution Manifest of the environmental impact of the project.
Pending, is a field visit for the expedition of environmental
compensation.
SCT: The
application was turned in October 1st and it is pending a
response.
Comisión Nacional
de Seguridad Nuclear y Salvaguardas: It is pending the purchase of Gamma Rays to
define the responsible party for its operation and training.